Tees Valley Lithium has agreed Heads of Terms with Wates Group to progress a Pre-Construction Services Agreement, marking the transition of the Project into its pre-construction phase.
Wates is a family owned UK contractor with recent experience delivering major industrial facilities, including in the battery industry. Under the forthcoming Pre-Construction Services Agreement, Wates will work alongside the TVL team to advance detailed engineering coordination, construction planning, programme development and cost alignment in preparation for Main Contract execution.
Transitioning from Development to Execution
With Front-End Engineering Design (FEED) now complete, the Project is moving into structured pre-construction execution. This phase will focus on:
• Detailed engineering coordination
• Construction methodology development
• Programme integration
• Procurement planning and long-lead equipment coordination
Early contractor involvement strengthens delivery readiness and enhances certainty around scope, sequencing and construction strategy.
Pre-construction activities are expected to commence in March 2026.
Preferred Site Confirmed
Following completion of the FEED study, which evaluated multiple site and tenure options, TVL has selected the 17.2-acre (7 hectare) New Road, Billingham site in Teesside as its preferred location.
Situated within an established chemical park with access to interconnecting utilities and services, the site provides the scale and infrastructure required for initial production and future expansion up to 100ktpa capacity. No material changes to the previously developed plant design are required.
Programme Remains Aligned
All core workstreams remain aligned to previously announced timelines.
Advancing pre-construction and long-lead coordination at this stage positions the Project to support targeted initial equipment deliveries from early 2027.
Building a Regional Supply Chain
TVL is committed to working with local suppliers and contractors wherever possible. Strong engagement at the Company’s supply chain event last year demonstrated the depth of industrial capability across Teesside, and the Project will continue to prioritise regional expertise as it progresses.
CEO Comment
Vikki Jeckell, CEO of Tees Valley Lithium, commented:
“Transitioning into pre-construction marks a significant step forward for the Project. We are now moving from development into disciplined execution planning.
Working with Wates strengthens our delivery capability, and we look forward to collaborating with local suppliers and partners as we advance. This facility represents a major opportunity for the region, for our shareholders and for the wider UK battery materials supply chain.”